Centrally Located Ambulance Station Timeline
08/27/2026

Upper Scioto Valley Ambulance District
Building Project Schedule
Pre-Construction & Permitting
- ๐ Permit Submittals: March 9, 2026 - Kicking off the journey!
- โ Permit Approvals: April 27, 2026 - Green light to build!
Site Preparation
- ๐๏ธ Site Setup: May 7, 2026 - Setting the stage for success.
- ๐ง๏ธ Stormwater & Drainage: May 18, 2026 - Keeping things flowing smoothly.
- ๐๏ธ Grading & Leveling: May 21, 2026 - Laying the groundwork.
- ๐ธ Groundbreaking Photo: June 25, 2026 - Capture the historic moment!
Structural Work
- ๐ง Undergrounds: August 24, 2026 - Digging deep for stability.
- ๐งฑ Footers / Foundations: September 8, 2026 - Building the strong base.
- ๐๏ธ SOG (Slab on Grade): September 14, 2026 - Solidifying the floor.
- ๐ฝ Septic and Leech Bed: September 21, 2026 - Installing essential site systems.
- ๐ Building Delivery: September 30, 2026 - The big arrival!
Exterior Construction
- ๐ Roof โ Insulations & Metal, Exterior Doors: October 19, 2026 - Sealing up the shelter.
- ๐งฐ Exterior Shell, Interior Framing, Masonry Work: November 9, 2026 - Shaping the structure.
- ๐ช Overhead Doors, MEP Rough-In, Drywall Hanging, Windows: November 30, 2026 - Adding the finishing touches.
Interior Construction
- ๐จ Drywall Finish: January 11, 2027 - Smoothing the surfaces.
- ๐๏ธ Paint โ Prime & First Coat: January 25, 2027 - Bringing color to life.
- ๐ ๏ธ Ceiling Grid/Edges, MEP Finals, Casework: February 1, 2027 - Finalizing details.
- ๐งน Flooring: February 5, 2027 - Setting the foundation underfoot.
- โจ Final Paint & Finish Work: February 15, 2027 - Polishing to perfection.
Finalization & Close-Out
- ๐ Inspections & Punchlist: March 1, 2027 - Quality check time.
- ๐ Final Inspection & Completion: March 10, 2027 - Celebration time! Project complete!
Notes
- This schedule is intended for public display.
- Dates reflect the official project timeline.
- Any changes will be updated and reposted